Caltrain construction, maintenance: July 24-30

Written by jrood

From Sunday, July 25, to Thursday, July 29, crews are continuing a project that will improve rail crossings at Mary and Sunnyvale avenues in Sunnyvale. Crews will grade and trench the site and install foundations for the improvements. They also will make wiring modifications in the signal houses. The work is part of a VTA project to improve safety at eight crossings in Sunnyvale, Mountain View and Palo Alto.

Monday, July 26, to
Thursday, July 29, crews will weld the tracks north of the 22nd street station.
Sunday, July 25, to Thursday, July 29, crews will resurface the tracks and
replace crossties from the San Antonio station to a little south of Lawrence
station. July 26-29, crews will resurface the tracks between the Lawrence and
Santa Clara stations. On July 25, crews welded the tracks near the San Jose
Diridon station.