Caltrain construction, maintenance update, 12/5-11

Written by jrood

Work on Caltrain's Grade Crossing Improvement Program, which will enhance safety at 25 grade crossings in San Mateo County, continues in Atherton and Menlo Park. Work will take place Dec. 5 and Dec. 7 - 10 between the hours of 8 p.m. and 4 a.m. at Fair Oaks Lane and Watkins Avenue in Atherton and Ravenswood and Oak Grove avenues in Menlo Park. Work also will be done from 10:00 p.m. Saturday, Dec. 5 to 1:00 a.m. Sunday, Dec. 6 at the Broadway crossing in Burlingame.

From Dec. 6 to Dec. 10,
crews will weld and grind the switches and replace crossties on the tracks
between the Bayshore and Millbrae stations. Dec. 7-10, crews will weld and
grind switches between the Menlo Park and Lawrence stations. Dec. 6-10, crews
will resurface the tracks and weld and grind the switches between the Sunnyvale
and San Jose Diridon stations.