Monday, April 12, 2010

Caltrain construction, maintenance update, April 11-20

Written by 

Work to reconstruct the pavement and track at the Villa Terrace crossing in San Mateo will begin April 16. The crossing will be closed from 8:00 a.m. Friday, April 16, until 6:00 a.m. Tuesday, April 20.

The work is part of a 10-week project to rebuild three railroad crossings in the cities of Burlingame and San Mateo. The work at Peninsula Avenue in Burlingame has been completed. After the Villa Terrace crossing has been competed, work will begin on the Bellevue Avenue crossing.

Work was done on fiber optic cables near the San Jose Diridon station April 9-11, from 9:00 p.m. until 6:00 a.m. the following morning.

On April 15, Caltrain will use a track geometry car to measure deviations in the tracks between San Francisco and San Jose. This on-track vehicle uses a sophisticated computer system to measure and record the alignment of the track.

April 11-15, crews will weld on the tracks in San Francisco and will replace crossties on the tracks between the South San Francisco and Millbrae stations.

April 11-16, crews will resurface the tracks between the San Mateo and Millbrae stations. April 12 and 13, crews will resurface the tracks between the Sunnyvale and Santa Clara stations.