Caltrain construction, maintenance update, May 22-28

Written by jrood

Between the hours of 8 p.m. Monday, May 24 and 4 a.m. Tuesday, May 25, crews will finish work on the grade crossing at Fair Oaks Lane in Atherton, Calif. The work, which includes installing a guardrail and pedestrian gates, is part of the San Mateo County Grade Crossing Improvement Project.  

From Sunday, May 23, to
Thursday, May 27, crews will replace crossties, weld and resurface the tracks
between the Bayshore and San Mateo stations. On May 23, crews welded on the
tracks between the Santa Clara and San Jose Diridon stations.