Stretching nearly four miles from east to west, the rail hub near North Baltimore will be largest CSX Transportation site for the shuffling of rail containers, the Sun Sentinel reports. Wood and Henry County officials took a tour of the sprawling site sitting on 500 acres running on the north side of Ohio 18, just outside North Baltimore.

"This is the crown
jewel of our network," CSXT spokesperson Dan Murphy said of the $175-million
site. "This is a rail Autobahn for us."

Murphy described the hub as
the equivalent of an airport terminal for rail containers. Like airports, where
passengers come in and get rerouted to different planes, the rail cars will do
the same type of shuffling with the help of massive cranes straddling eight
tracks. It has been estimated that one intermodal train takes 280 semi-trucks
off the highway, Murphy said.

As the small bus crawled
through the intermodal hub, the passengers marveled at the work that had
already been done and the work that is planned in the near future. They passed
mountains of rail ties waiting to be laid, railroad cars delivering stretches
of rail and workers welding together some of the 24 miles of track that will
cover the site.

Of the 500 acres, CSXT will
initially use 280 acres. The railroad’s next largest hub is 250 acres in
Bedford Park in Chicago.

An earthen berm already
lines Route 18. A concrete plant has been erected on site. Two 250,000-gallon
diesel fuel tanks are being built. And several retention ponds have been
constructed, with the excavated dirt being used to elevate the remaining 500
acres by 3.5 feet, according to Jim Caffrey, resident engineer with Jacobs
Engineering.

"This will be a very
busy area just a few weeks from now," Caffrey said, pointing to the area
where the towering cranes will be erected.

The five cranes are
scheduled to arrive in the port of Toledo in June. The 100-feet high cranes
will span 306 feet, covering all eight tracks underneath them. The electric
cranes, which will be nearly silent, actually generate energy when lowering the
container boxes onto different trains.

"We’re doing a lot to
make this a green facility," Murphy said.

A $6-million crane
simulator is being constructed on site to train employees how to use the real
cranes, Caffrey explained.

Construction of the hub is
expected to be complete by the end of December, with the site being operational
by April.

Now local and state
officials are working on improvements to Route 18 and widening of Interstate
75. The county commissioners approved a resolution asking the state to widen
I-75 to three lanes to make room for all the additional traffic expected with
the rail hub.