Metro-North to install ties, perform catenary work

Written by jrood

Installation of concrete ties on the New Haven Line between the New York and the Connecticut state line and at the Stamford Station is entering its final phase this spring. Between March 21 and June 26, Metro-North Railroad will be replacing concrete ties on the outbound local track (Track 4) from Rye to Greenwich. Preparation work for and installation of concrete ties at Stamford Station will result in track changes at Stamford from March 23 until April 1. This project, along with continuing catenary replacement work, greatly limits Metro-North's operating flexibility on the New Haven Line, normally a four-track railroad, as there are fewer tracks available to use for train service.