Minnesota’s Northstar commute line advancin

Written by 
At the downtown Minneapolis LRT Connection for the Northstar commuter railroad, crews finished glass installation at the LRT platforms. Communications system testing and programming finished at both the LRT and Northstar stations. Crews began installation of the handrail on the LRT platform. The overhead catenary system wires are now live.
In Coon Rapids, Anoka, Elk River and Big Lake, Punchlist work continues at the suburban stations this week.

 

In Fridley, crews began pouring concrete for the station platform, including the footings for the ticket vending machines. This work will continue through the week of August 10. Forming and pouring of the east head house walls finished. Crews began setting the structural steel at the station platform. Structural steel work will continue through the week of August 10 at the platform and crews will begin setting the structural steel at the east head house.