In Fridley, crews began pouring concrete for the station platform, including the footings for the ticket vending machines. This work will continue through the week of August 10. Forming and pouring of the east head house walls finished. Crews began setting the structural steel at the station platform. Structural steel work will continue through the week of August 10 at the platform and crews will begin setting the structural steel at the east head house.