Minnesota’s Northstar Fridley Station work continues

Written by jrood

At the Northstar commuter rail station in Fridley, Minn., installation of station platform pavers was completed and roofing on the station shelters and east and west entrances continues. Installation of glass for the station shelters and east and west entrances has begun. Painting of the steel on the station platform and the east and west entrances is completed for now and will continue after glass installation occurs.

The majority of electrical
work at the station is completed. The majority of work in the tunnel is
completed. Work on the elevators is on hold until the elevator cabs arrive in
mid-October. Installation of the irrigation system on the east sand west sides is
completed. Landscape planting on the east sand west sides continues, as does fence
installation around the station site.