Northstar commuter rail work continues in Twin Cities

Written by jrood

LRT and Northstar system testing continue. Painting and striping of the streets in the project area was completed. Punchlist work is ongoing at the Northstar and LRT stations. Punchlist work continues at the suburban stations.

In Fridley, concrete pours
for sidewalks on the west side will be completed the week of Sept. 21. Installation
of station platform pavers will be also completed that week, as will installation
of window sills, rain gutters, door frames and roof decking. Painting of the
steel on the station platform and the east and west entrances is scheduled to
continue. Continuing work includes electrical work in the tunnel, work on the
elevators, and Installation of the irrigation system on the east and west sides.
Milling and paving of 61st Way is on hold for now.