Metro-North details results of track work initiative

Written by Jenifer Nunez, assistant editor
image description
Metro-North

Metropolitan Transportation Authority's (MTA) Metro-North Railroad has detailed its latest results of a systemwide track reconstruction effort that has rebuilt miles of the railroad in the past two and a half years, delivering smoother, safer and more reliable service to customers.

 

Since May 2013, Metro-North workers have replaced 97,961 ties, laid 16.5 miles of continuous welded rails, rebuilt 88 switches, renewed and/or upgraded 32 railroad crossings and performed 2,905 welds on joints that connect stretches of track with one another.

“The reconstruction work has significantly enhanced the state of our infrastructure,” said Joseph Giulietti, president of Metro-North Railroad. “Our rails are safer today as a result of this concerted increase in track renewal work. This is a team effort that requires the coordination of dispatch operations and the dedication of our employees to be able to accomplish.”

In addition to visual track inspections, which are conducted twice a week by inspectors who are positioned within the track being inspected, Metro-North’s track reconstruction and renewal efforts have been guided by a spectrum of detailed track inspections.

To measure a variety of geometric parameters of its track, including the position, curvature, alignment, smoothness and the cross level of the two running rails, Metro-North employs track geometry cars operated by the Federal Railroad Administration and Mermec. The cars use a variety of sensors, measuring systems and data management systems to create a profile of the track being inspected.

To detect flaws, defects and metal fatigue inside the steel running rails that trains roll over, Metro-North has worked with Sperry Rail Service, which operates a specialized car over rails and measures them with ultrasonic and induction test equipment.

To identify any instances where the end of a rail does not match up precisely with the beginning of the following rail, the railroad has employed Georgetown Rail Equipment Company’s Aurora System.

Metro-North uses a track loading vehicle to give rails a stress test, applying forces close to the strength limits of the rails, ties, rail fasteners and ballast. The commuter railroad also uses ground-penetrating radar to show potential problem areas in the structural layers below the track’s surface.

If and when any of these inspections and tests identify defects along the rails, crews assess the magnitude of defect and make immediate repairs or, for minor defects, institute speed restrictions over selected segments of track until the repairs are made.

 