NYCT installs composite ties as part of Staten Island project

Written by Jenifer Nunez, assistant editor
image description
NYCT installed 7,500 of Axion’s ECOTRAX® ties installed as part of the St. George Renewal Project.
NYCT/MTA

As Earth Day approaches and as part of recommendations from a blue-ribbon commission tasked with reducing the impact of public transit on the environment, Metropolitan Transportation Authority (MTA) New York City Transit (NYCT) has installed approximately 6,500 sustainable composite ties in a major Staten Island Railway (SIR)

track renewal project to repair significant damage caused by Superstorm Sandy.

The St. George SIR terminal is undergoing a major track and switch reconstruction project as the railway continues to recover from Sandy-related damage. Prior to the storm in October 2012, a terminal rehabilitation project had been planned to repair and update signals, switches and track. Sandy made the project critical when storm surge flooded SIR tracks and the entire St. George yard complex with corrosive saltwater, highlighting areas where flood protection or protective infrastructure needed to be installed. The saltwater significantly damaged all 12 tracks, multiple switches, equipment and cables, as well as facilities and the train control tower.

“With careful planning and foresight, we took this opportunity to not only make critical Sandy-related repairs but to do it better using environmentally friendly materials,” said Doug Connett, vice president and chief officer for Staten Island Railway.

NYCT started the St. George renewal project in September 2014, with plans to integrate resiliency measures while replacing outdated or damaged equipment and making repairs. Those resiliency measures include raising signal equipment to 72 inches above the tracks, raising platforms for battery and generator enclosures and installing a new third rail system.

Repairs at St. George include the replacement of 12,000 linear feet of track and installation of a total of approximately 7,500 high-density plastic rail ties. The ties, which are made of 100 percent recycled materials, were manufactured by Axion International.

The change in track tie materials from wood to high-density plastic stems from a recommendation made by the MTA’s Blue Ribbon Commission on Sustainability, which released a report in 2009 on ways to operate a greener transit system throughout the New York area. The commission’s final report made nearly 100 recommendations to reduce the MTA’s carbon footprint while generating savings and economic growth, one of which included a recommendation that the MTA expand procurement of sustainable railroad ties across all rail agencies.

The $105-million St. George Terminal project is taking place with no service interruptions to customers and is 55 percent complete with composite tie installation to be completed by June 1.