The State Full Funding Grant Agreement will provide 25 percent of the funding for the LYNX Blue Line Extension from Center City Charlotte to the UNC Charlotte campus. The support also prepares the system to receive a full funding grant agreement of 50 percent of the project costs from the Federal Transit Administration later this year.
The 9.4-mile alignment would run from Uptown Charlotte to the UNC Charlotte campus and include 11 light-rail stations and four parking facilities. Construction of the $1.16 billion BLE Project is scheduled to begin fall 2013 with operational service expected in 2017.