WMATA releases final SafeTrack plan

Written by Jenifer Nunez, assistant editor
image description

The Washington Metropolitan Transportation Authority (WMATA) released the final SafeTrack plan – a maintenance effort that will accelerate three years worth of work into approximately one year.

 

The plan significantly expands maintenance time on weekends, weeknights and midday hours and includes 15 “Safety Surges”– long-duration track outages for major projects in key parts of the system. The plan addresses Federal Transit Administration (FTA) and National Transportation Safety Board (NTSB) safety recommendations and deferred maintenance backlogs while restoring track infrastructure to good health.

Following review and collaboration with FTA, as well as consideration of traffic mitigation and alternate travel options by the Department of Transportation (DOT) agencies in the District of Columbia, Maryland and Virginia, regional law enforcement, Office of Personnel Management, Department of Homeland Security and General Services Administration, the implementation of SafeTrack will commence immediately.

“I am encouraged by the region’s response to SafeTrack and appreciate the support of business and community leaders, jurisdictional officials, our congressional delegation and most importantly the riders, who have rallied to help us get through this challenging work,” said WMATA General Manager and Chief Executive Officer Paul Wiedefeld. “I also want to recognize FTA for their collaboration and guidance, which is reflected in the final plan.”

In addition to the Safety Surge projects, SafeTrack also includes closing the Metrorail system at midnight every night (rather than at 3 a.m. on Friday and Saturday nights) and expanding weekday maintenance opportunities by starting selected work at 8 p.m., rather than 10 p.m.

Each of the 15 Surge projects will result in either around-the-clock single tracking or shutdowns of selected track segments and will have a significant impact on rush-hour commutes. Many of the Surges will severely reduce the frequency of trains, resulting in crowding and extended wait times.

“Safety comes first and I want to remind the region that SafeTrack is not just about the 15 maintenance surges,” said Wiedefeld. “SafeTrack also includes weeknight work that will require single track operations in sections starting at 8 p.m.; it means closing the system at midnight on weekends as opposed to 3 a.m. and committing to a moratorium on extra hours of early morning or late night service when it conflicts with trackwork.”

The first Surge project will begin June 4 and involves continuous single tracking between East Falls Church and Ballston stations while miles of deteriorated wood ties are removed, the substructure of the railroad is rebuilt and new ties, fasteners, ballast and other infrastructure is installed. The duration of this project is 13 days and will result in reduced service at all Orange and Silver line stations, especially those stations west of Ballston where trains will only run every 18 minutes.

Independent verification and inspection of trackwork will be performed regularly to ensure that the work is being done correctly and efficiently.

 