Valley Transportation Authority moves forward on Phase II extension project

The Valley Transportation Authority is moving forward on the BART Phase II extension.

VTA votes on ‘foundational backbone’ of BART extension project

At the VTA Board of Directors meeting on May 5 the VTA Board will vote on a contract for the initial stage of the tunnel and trackwork, known as Contract Package 2 (CP2) for VTA’s BART Silicon Valley Phase II Extension (BSVII) Project.

Bells & Whistles—A double-decker punch?

The top news stories RT&S was following the week ending April 29.

BART extension project into San Jose now facing $1.6B funding gap

The Santa Clara Valley Transportation Authority wants the one thing that has never been done before in the U.S. to be, well, done. However, it is not a done deal.

BART continues cable work and single tracking

BART continues its work on replacing old power cables throughout its system. The latest news is that there will be single-tracking in Orinda for two weekends in April so this work can continue.

‘Don’t think you can’t do it’: Women in engineering at BART on their triumphs and challenges

As part of Women’s History Month, BART showcased the contributions of three of the women on their engineering team.

BART track shutdown–Buses replace trains for 10 weekends in 2022

A large BART construction project is now underway in southern Alameda County.

BART Red line service restored March 22

RT&S reported on March 9 that BART suspended Red line service due to a damaged power cable. Here is an update on that story.

BART suspends Red Line service, Orange Line only between Richmond and MacArthur

On Sunday, March 6, BART experienced a power traction cable fault (or break) between El Cerrito Plaza and Ashby stations.

BART single tracking through Lafayette for cable work (next Sunday single tracking 1/23/22)

BART is replacing electrical lines and other support components that are critical for maintaining reliable train service through Lafayette.

BART undertaking critical cable replacement work in Lafayette

BART is replacing electrical lines and other support components that are critical for maintaining reliable train service through Lafayette.

BART single-tracking in some areas to complete critical electrical work

BART has several projects underway to replace sections of its critical electrical network that powers their trains.

RT&S November issue now online

The November issue of RT&S contains a feature story on BART’s rail grinding program.

A project first will receive billions in federal funding

The first Expedited Project Delivery (EPD) Pilot Program project is closer to reality today after the U.S. DOT advanced Santa Clara Valley Transportation Authority’s (VTA’s) Bay Area Rapid Transit (BART) Silicon Valley Phase II project.

BART continues to work on traction power cable replacement

BART crews will be working in southern Alameda County to replace 34.5 kV (kilovolt) traction power cables that provide electricity for trains.

BART announces additional cable and rail replacement

BART has announced additional work and maintenance on the railroad.

Repair work begins on BART’s traction power cables between El Cerrito Plaza and El Cerrito del Norte stations

BART has been working on its planned rebuilding program, but an electrical line failure has expanded the scope of the work.

Accelerated work during the pandemic advances BART rebuilding effort to new milestone

BART managed to leverage pandemic downtime to push forward their rebuilding work.

BART construction project begins in southern Alameda County

BART’s southern Alameda County track replacement project has begun.

COVID: We’re not out of the woods yet, and transit companies continue significant precautions

COVID is still a major threat to the United States.

LOAD MORE