| Wisconsin & Southern installing cwr on Madison Sub |
|
|
|
| Friday, October 29, 2010 | |
|
Wisconsin & Southern Railroad Co. continues with its welded rail installation on the Madison Sub. As of October, 14 miles of rail have already been installed by crews, extending from Vincent Street at Milton Jct. to just east of Stoughton, Wis. M/W forces are currently focusing on dumping ballast on the track and raising and tamping for final alignment before winter freeze-up.
|