MDOT MTA Purple Line Newsletter Released for March 2025

Written by Jennifer McLawhorn, Managing Editor
image description
Maryland Transit Administration Purple Line Train
Maryland Transit Administration

BALTIMORE - The MDOT MTA released its Purple Line Newsletter for March 2025 with construction updates.

In the newsletter, Purple Line Senior Project Director for MTA, Ray Biggs II wrote that the Purple Line is now 76% complete. Currently, 20 stations are under construction, and 67,500 feet of track has been installed. At the Glenridge Operations and Maintenance Facility, or OMF, crews continue to install the Overhead Catenary System poles and track switches.

Additionally, the newsletter spotlights the two all-female Purple Line teams in honor of Women’s History Month with interviews with Mia Riley and Niambi Jarvis.