In downtown Minneapolis, crews will mill and pave the LRT track area the week of August 24. There will be no impact to vehicular or pedestrian traffic. Communications system testing and programming continued at both the LRT and Northstar stations. The overhead catenary system wires are now live.
At the Fridley Norhtstar Station, crews continued concrete pours for the station platform; concrete work on the platform will continue the week of August 24. Preparation for curb and gutter work on the north side of 61st Way is scheduled to be completed the week of August 24. Once the curb and gutter work is complete, crews will begin work on the cul-de-sac at the east end of 61st Way. Crews finished setting the structural steel for the center head house and will begin setting the structural steel at the east head house. Painting of the steel on the station platform is scheduled to begin the week of August 24. Work in the tunnel continues with tiling to occur the week of August 24.
