SFMTA Central Subway Tunnel structure complete

Written by Jenifer Nunez, assistant editor
image description
The tunnel portal will be the entrance and exit point for future light-rail service on the Central Subway.
Central Subway

The San Francisco Municipal Transportation Agency's (SFMTA) Central Subway tunnel portal entrance, which was the final element to the overall tunneling contract, is now finished. SFMTA says this portion of the Central Subway Project was completed on-time and on-budget.

 

The portal, at 4th and Harrison streets, was initially called the “launch box” because it served as the entrance site of two 350-foot-long boring machines (TBMs). Each 750-ton TBM tunneled 8,500 feet beneath SoMa, Union Square and Chinatown creating the Central Subway tunnels. Now that the TBMs have completed their 1.5-mile journeys, the launch box has been seismically and structurally reinforced creating the portal where the Muni Metro T Third Line Light Rail Vehicles will enter and exit the Central Subway.

The tunnel portal structure contract called for a final completion date of May 15, 2015. However, the crews met expectations by substantially completing the portal structure, constructing the twin tunnels and five cross passages a month earlier.

“It was not only imperative that the portal structure create San Francisco’s next generation of public transit,” said Ed Reiskin, SFMTA director of transportation. “It was crucial that we adhered to our commitment to the public. We promised to deliver on-time and on-budget and the completion of this portion of the project is another milestone that demonstrates we deliver as promised.”

The project was complete within budget estimates of $241 million. The U.S. Department of Transportation gave approval of the Full Funding Grant Agreement of $942.2 million to fund nearly half of the Central Subway Project. The remaining budget is balanced by existing state and local grant funds.

The Central Subway is expected to open to the public in 2019.