Illinois high-speed project wraps up track and tie replacement

Written by Jenifer Nunez, assistant editor
image description
Illinois Department of Transportation

The Illinois high-speed rail project connecting Chicago to St. Louis reached a significant milestone in construction September 22, 2014, when the last segment of track and crossties were replaced.

 

“High-speed rail service will create jobs and open new economic development opportunities across Illinois,” Illinois Gov. Pat Quinn said. “The work done today will help residents get to their destinations quickly and efficiently for years to come. I am proud that our state is leading the way on this transportation trend of the future.”

The Chicago to St. Louis high-speed rail project is on schedule to reduce the five and a half hour trip between the two cities by 30 minutes at the end of 2015 and another 30 minutes by the end of 2017. By the end of 2015, more than two-thirds of the corridor will be capable of hosting trains running at 110 mph, compared to just 15 miles today between Dwight and Pontiac.

 

Gov. Quinn’s Illinois Jobs Now! capital construction program is contributing nearly $400 million toward the Chicago to St. Louis high-speed rail project as a match to the $1.3 billion the state has received from the federal government.

In addition to the track and crosstie work, crews are continuing to improve the nearly 300 grade crossings along the corridor, adding four-quadrant gates at all public and private crossings and dual gates at farm and pedestrian crossings.

Later this year and in 2015, installation will begin of the positive train control signaling system. Union Pacific is building or extending 13 new sidings that have been designed to provide passing tracks that will permit passenger and freight train traffic to flow smoothly and make the Chicago-St. Louis service more reliable.

“Working together with the Illinois Department of Transportation and the Federal Railroad Administration, we have made great strides on this important public – private partnership,” said Donna Kush, Union Pacific vice president public affairs, Northern Region. “Our engineering team has produced some very impressive numbers since this project started in 2010 by installing about 500 miles of rail and nearly 650,000 concrete ties, while spreading more than 1.3 million tons of ballast to help provide a safe and stable roadbed.”

The corridor will receive all new railcars and locomotives over time, beginning with initial deliveries in summer 2016.

To date, the construction project on the Chicago to St. Louis high-speed rail corridor has upgraded more than 2.6 million linear feet of rail, added more than 1.3 million tons of ballast, replaced 646,000 ties, installed 225 interim crossings and finalized 33 crossings.

 

 