East Side Access trackwork to speed LIRR and Amtrak trains
For 30 days this summer, crews working on the New York Metropolitan Transportation Authority’s East Side Access megaproject will build heavy concrete slabs that will serve as the ceiling of a new underpass at the busy Harold Interlocking switching complex in Sunnyside, Queens.