NJT: New bridge over troubled waters

Written by William C. Vantuono, Editor-In-Chief, Railway Age
image description
Westbound NJT North Jersey Coast Line train on River Draw. William C. Vantuono photo.

The Gateway Program's Portal North has been in the news lately. A project south of Portal North deserves equal attention.

Portal North, the new Gateway Program fixed-span bridge on the Northeast Corridor (NEC) situated between New Jersey and New York that will replace 112-year-old moveable-span Portal Bridge, has been getting the bulk of public and political attention in recent years. But some 35 miles southwest, on the electrified portion of NJ Transit’s North Jersey Coast Line (NJCL), there’s another bridge replacement project of perhaps equal importance. This one is located on the Raritan River, between Perth Amboy and South Amboy, N.J.

Quietly proceeding, on schedule, is NJT’s Raritan River Bridge Replacement Project. The existing bridge, a 114-year-old, 2,931-foot-long (abutment to abutment) double-track structure with a swing span, was built in 1908. Known as River Draw, it suffered severe damage during Hurricane Sandy in 2012 when it was struck by a runaway tugboat, shifting it 18 inches on its pilings and requiring more than $3 million worth of emergency repairs before being placed back in service, albeit with speed restrictions. 

NJT illustration

Replacing River Draw is important as it is the only rail connection between the 17 stations on the North Jersey Coast Line south of the Raritan River and the New Jersey/New York metropolitan region encompassing greater Newark, Hoboken, Jersey City and New York City. The NJCL, which connects with the NEC south of Penn Station Newark, provides service to approximately 11,400 daily riders making approximately 23,000 average weekday passenger trips, and also accommodates Conrail Shared Assets freight rail services. 

NJT photo

The new bridge, estimated to enter service sometime in 2026, will be the third railroad bridge at this location. River Draw, which in 1908 cost $1 million, replaced a swing span built in 1875 for the New York & Long Branch Railroad, which was jointly operated by the Central Railroad of New Jersey and Pennsylvania Railroad. In 1936, the NY&LB became part of the PRR’s electrified territory in the Northeast when the PRR extended the catenary on its New York-Washington D.C. main line (today’s NEC) from Philadelphia to Washington. The wire terminated at South Amboy, prompting motive power changes there from electric locomotives to steam (through 1957) and then diesel, for service to Bay Head. (NJT extended NJCL electrification to Aberdeen-Matawan in 1982 and Long Branch in 1988.)

The 1875 bridge, an engineering marvel for its day, needed replacement after less than 50 years of service because train weights and speeds had increased significantly during that time period. The current 1908 structure has had no fewer than four owners: NY&LB (PRR and CNJ operations), Penn Central, the New Jersey DOT (PC and then Conrail operations), and, since 1983, NJT. This third iteration, which when completed is projected to cost well over $800 million, is designed to last at least as long as what it’s replacing, if not longer. 

William C. Vantuono photo

NJT developed four goals for this project, each with a set of objectives:

  1. Improve resilience of the Raritan River bridge to severe storms.
    1. Improve bridge’s resistance to ocean surges.
    2. Raise tracks and electrical/mechanical systems above NJT’s Design Flood Elevation (2.5 feet above the Federal Emergency Management Agency’s Base Flood Elevation) to the extent practicable.
    3. Design vulnerable components to better withstand saltwater and ocean surges.
    4. Provide adequate structural capacity to comply with current code requirements.
    5. Minimize loss of service on the North Jersey Coast Line during and following storms.
  2. Provide rail improvements that minimize service disruption and optimize operations.
    1. Optimize design speeds for trains on the bridge, up to 60 mph.
    2. Avoid substantial compromises to existing NJCL timetables.
    3. Accommodate heavier freight trains with railcars of 286,000 pounds GRL (gross rail load) and potentially up to 315,000 pounds.
    4. Minimize capital and operating and maintenance costs.
    5. Implement within a reasonable timeframe.
    6. Avoid impacts to NJCL and Conrail operations during construction.
  3. Maintain and improve marine navigation beneath the bridge.
    1. Minimize delays to marine traffic due to bridge malfunctions.
    2. Widen channel to minimize the risk of collisions with marine vessels.
    3. Enable the safer and faster passage of boats beneath the structure.
    4. Avoid impacts to marine traffic during construction.
  4. Minimize adverse impacts on the built and natural environment.
    1. Avoid property acquisition to the maximum extent feasible.
    2. Avoid, minimize or mitigate adverse impacts on historic resources.
    3. Avoid impacts on parklands, open space, natural features and coastal waters.
    4. Maintain access to nearby residences and businesses during construction.
    5. Minimize construction impacts to the extent feasible.
William C. Vantuono photo
William C. Vantuono photo

NJT considered five bridge replacement options, ultimately selecting a double-track, moveable-span vertical-lift design located to the west of the existing bridge. The alignment is about 10 degrees off-axis from the current bridge, with the center span perpendicular to the river’s navigation channel, providing improved vertical, horizontal and navigation channel geometry. Compared to the existing bridge, it is 10 feet higher, above a 100-year flood elevation, with 300 feet of clear navigation width to lessen the risk of vessel collision. Its mechanical and electrical systems are far less complex and thus more reliable and less maintenance-intensive than that of a swing span.

William C. Vantuono photo

Raritan River Bridge Replacement is a three-phase project. NJT in May 2020 awarded a $248 million contract to George Harms Construction Co. of Farmingdale, N.J. for Phase 1, “GC.01.” Work, expected to be completed in October 2024, includes landside and bridge approaches and substructure. Phase 2, GC.02 (currently in procurement), will include construction of the vertical lift bridge (lift/flanking span superstructure), and communications, signal and overhead catenary work. Phase 3, GC.03, includes demolition of the existing bridge.

Old stone piers contrast sharply with new concrete piers. William C. Vantuono photo

GC.01 lays the new bridge’s foundation with impressive numbers: Its 84 8-foot, 6-inch diameter drilled shafts, which are between 180 and 240 feet long, have been completed. Each shaft has a casing length of between 60 and 145 feet. There is a total of 36,258.5 cubic yards (CY) of concrete in these shafts. Ten of 26 pier caps have been finished. These consist of 18 bent piers (2 drilled shafts), 4 quad piers (4 drilled shafts), 2 flanking spans (6 drilled shafts), and 2 lift spans (10 drilled shafts). In total, there are 17,010 CY of concrete and 2.5 million pounds (1,300 tons) of rebar in the pier caps. NJT notes that “there’s enough concrete in the drilled shafts to build a sidewalk from South Amboy to Cape May, N.J.” That’s 127 miles.

William C. Vantuono photo

The total cost for all three project phases is estimated at $880 million, of which $446 million is financed by a Federal Transit Administration Emergency Relief Program grant for resilience projects in response to Hurricane Sandy. NJT allocated $248 million, or 44%, of the FTA grant to finance 100% of GC.01. The project is also part of NJT’s five-year capital plan.

Rendering of new completed bridge. AECOM/Mott MacDonald illustration

“The Raritan River Bridge replacement is a great step forward in ensuring our North Jersey Coast Line customers have robust and sustainable rail service that will better withstand the effects of extreme weather, while meeting the current and future transportation needs of our customers for many decades to come,” remarked NJ Transit President and CEO and Kevin Corbett, who hosted an Aug. 3 tour of the construction sight complete with a water cruise in a small George Harms personnel shuttle boat on the river. 

WNBC News-New York New Jersey Correspondent Brian Thompson (right) with NJT President and CEO Kevin Corbett. William C. Vantuono photo.

Editor’s Note: As a former long-time NJCL commuter (permanently working from home since late 2019) and the last president of the long-defunct (1933-2012) Jersey Shore Commuter’s Club, which leased a private car from NJT and predecessors PRR and Penn Central, I traveled across the existing bridge more than 12,000 times over the course of more than 20 years. Those interested in exploring the history of River Draw and its 1875 predecessor beyond what I’ve presented above should check out Morgan-NJ.org. Another excellent source is “The Unique New York & Long Branch” by Don Wood, Tom Gallo and Joel Rosenbaum, available on Amazon. – William C. Vantuono

PRR North Jersey Coast commuter train on Raritan Draw, back in the day.