Making sure utilities are working properly is a big part of the puzzle as construction progresses on the Hazel McCallion Line (also known as the Hurontario LRT).

Crews are upgrading and relocating utilities (like sewers and telecommunications cables) as part of the construction of the new transit line.

This is essential for widening the roads and making room for the brand-new LRT line.

Wet utilities vs dry utilities

This work includes both “dry utilities,” namely the installation of electric, and telecommunications infrastructure, and “wet utilities,” which include sanitary and storm sewers, plus watermains.

One of the areas where a lot of this work is taking place is between Lakeshore Road East and the Queen Elizabeth Way (QEW).

Mississauga South

Mississauga South presents unique challenges when performing utility works, as the roadway is much narrower than other parts north along Hurontario Street.

As a result, crews must take extra steps to ensure work is accomplished safely and in a timely manner while minimizing impacts.

Mississauga South subdrain installation. (Metrolinx image)

Wet utility work

The installation of upgraded watermains, as well as storm and sanitary sewers, continues to progress steadily along Hurontario Street from Eaglewood Boulevard to the QEW.

The work area has now shifted from the east side of Hurontario Street to the west, between Park Street and Inglewood Drive. Across the board, work has been happening on the east side of Hurontario Street and then shifting to the west side of the roadway in Mississauga South.

This is to reduce the impact on traffic in areas where the road is narrower.

Dry utility work

Directional drilling to create underground Alectra duct banks that cross Hurontario will be taking place in the fall of 2022 to support a switch over to newly upgraded power service. The relocation of power lines along Hurontario Street will allow for road widening and sufficient clearances for the overhead catenary system (OCS).

Dry utility cable pulling in Mississauga Centre area. (Metrolinx image)

“One of the many benefits of this work is that a significant amount of wiring and cables are being moved underground – improving the appearance of the local area,” said Abdul Kader Azzam, project manager of dry utilities at Mobilinx, the constructor for the Hurontario LRT.

“This will also help prevent damages and offer protection to power lines from strong winds and other harsh weather conditions,” Azzam said.

Other ongoing construction

Utility works have also been taking place in Cooksville, Mississauga Centre, Mississauga North and Brampton. Some of these works include:

Cooksville

  • The installation of watermain, storm, and sanitary systems in various areas along the west side of Hurontario between Harborn Road and Matthews Gate, taking place now.
Wet utilities relocations in Cooksville. (Metrolinx photo)
  • Crews are currently installing Alectra utilities near Harborn Road and will progress north in the coming months. 

In the coming weeks, crews will continue to install Alectra duct banks in the area between Queensway and north of Paisley.

Mississauga Centre

  • In advance of guideway and track construction for the LRT, crews have been installing track catch basins and storm drainage crossings in various locations like: Rathburn Road, Hammerson Drive and Station Gate Road
  • This infrastructure will mitigate potential flooding and allow for storm water to drain away from the LRT tracks and into the appropriate storm drains once complete.

Mississauga North

  • Crews are continuing with the installation of an Alectra duct bank at the southwest corner of Britannia Road towards Armdale Road.
  • New electrical poles near Derry Road are currently being installed with the use of cranes.
Dry utility relocations in North Mississauga. (Metrolinx photo)

Brampton

  • Construction staging expands along Hurontario Street as utility relocations, storm installations, ductbank installations and road widening works continue. 
  • This is in preparation for guideway and track installations that will take place in the center of the roadway
Watermain installations at OMSF near Kennedy Road (Brampton)