Caltrain electrification project

Caltrain OCS Fully Energized

From Our Colleagues at Railway Age:

SAN CARLOS, Calif. ––Caltrain, with partners Pacific Gas & Electric Company (PG&E) and Balfour Beatty, have energized and tested the OCS (overhead catenary system) on the entire 51-mile Caltrain Electrification Project between San Francisco and San Jose. The next step is testing the system’s Stadler Rail-built EMUs (electric multiple-units) at maximum operating speed and prepare for electrified revenue service, expected to commence in September 2024.

Caltrain to Reduce Service for Electrification Construction

Caltrain announced on Nov. 28 that it will temporarily reduce service from Monday, Dec. 5, through Sunday, Dec. 18 to accommodate electrification construction that includes signal cutover work at 16 grade crossings, requiring a 24/7 single-tracking window between Belmont and Mountain View.