Caltrain construction, maintenance Oct. 17 – 23

Written by jrood

Work on Caltrain's Grade Crossing Improvement Program, which will enhance safety at 25 grade crossings in San Mateo County, continues in Burlingame, Menlo Park and Atherton. Throughout the project area, at least one lane of the impacted street will remain open. Flagmen will direct traffic and pedestrians around the construction.

Work continues on a $2.8-million
project to add additional signals to the Caltrain signal system.

A $2.1-million project to
improve the radio communications system that operates the signals and switches
on the railroad tracks is underway. The project will add a second radio
channel, which will increase the system’s capacity. Work will take place Oct.
17-23 between the hours of 7:00 p.m. and 4 a.m. at several locations near San
Francisco and the Diridon and Tamien stations in San Jose.

The City of Sunnyvale has
closed the Wolfe Road Bridge for repairs. Although the four-lane bridge crosses
the Caltrain tracks, there will be no impact to Caltrain service.

From Sunday, Oct. 18 to
Thursday, Oct. 22, crews will replace worn track panels and cross ties on the
tracks between the San Francisco and Millbrae stations. Oct. 18-20, crews will
weld and grind the switches, and replace worn asphalt, rails, ties and ballast
on the tracks between the Belmont and Menlo Park stations.

Oct. 21-22, crews will weld
and grind the switches and replace worn asphalt, rails, ties and ballast on the
tracks near the Redwood City station.