Harrisburg Line Track Renewal Project Moves to Phase 3

Written by Jennifer McLawhorn, Managing Editor
image description
Harrisburg Line Track Work Progress
Courtesy of Amtrak

HARRISBURG, Pa. – Amtrak’s Harrisburg Line Track Renewal project will enter phase three on Monday, June 10th.

The project would be estimated to take two years to complete between Lancaster and Harrisburg. However, Amtrak states that it is approaching the project with “single and full track outages to improve work efficiencies and reduce the duration of customer impacts.” The $122 million project is expected to be completed in November, and the release states the “work progress has been advancing ahead of schedule.” On April 30th, RT&S reported the project had moved to phase 2.

This will lead to minor schedule changes for some Keystone Service trains during both the weekend and on the weekdays. Amtrak reports Pennsylvanian train schedules are unaffected. Below is a full list from Amtrak of changes to train schedules:

Monday – Thursday 

  • No changes to the truncated trains: 646, 648, 650, 652; 607, 641, 643, 645 
  • Will operate same schedule as today: 640; 657 
  • Minor departure/arrival adjustments: 600, 642; 609, 651, 653, 655 
  • Schedule adjustments of 10 minutes or more: 644, 654, 656, 618, 620, 622; 601, 605, 647, 649 

Friday 

  • Will operate same schedule as today: 640, 646; 609, 655, 657 
  • Minor departure/arrival adjustments: 600; 607, 641, 643, 651, 653 
  • Schedule adjustments of 10 minutes or more: 642, 644, 648, 650, 652, 654, 656, 658, 620, 624; 601, 605, 645, 647, 649 

Saturday – Sunday 

  • Will operate same schedule as today: 666, 672, 674, 610; 663, 665, 615, 667, 669, 671 
  • Minor departure/arrival adjustments: 660, 662 
  • Schedule adjustments of 10 minutes or more: 664, 670, 612: 661, 611, 661 