Valley Metro building new track in downtown Phoenix

Written by David C. Lester, Editor-in-Chief
image description
Valley Metro is building new track in downtown Phoenix.
Valley Metro

It seems that transit construction stories abound these days. This reflects a commitment of local government and transit agencies to provide strong transit infrastructure to efficiently move passengers in and around cities, providing passenger convenience and environmental benefits.

Below, Valley Metro in Phoenix reports on its latest construction work.

“Construction progress continues on the South Central Extension/Downtown Hub light rail project in Phoenix. Crews are about to begin work that will connect the current and future lines, creating a two-line light rail system and transfer hub in downtown Phoenix by 2024. This spring, workers will install nine new pieces of special track, reconstruct more than 1,000 feet of track and build one station foundation as part of the Downtown Hub.

Workers inspect special trackwork installed March 2021 (Valley Metro Photo)

“To make this important track connection, construction will occur on the existing light rail trackway. As a result, from April 16-July 2, all light rail trains are estimated to arrive at station platforms every 20 minutes throughout the service day. Riders are asked to plan ahead to ensure timely arrivals at their destinations.

“In addition to the temporary rail schedule, some stations in downtown Phoenix will be closed. Learn more about the station closures that will be in effect at valleymetro.org/pardonourprogress. View the full schedule and plan your trips on the Valley Metro App or through the Trip Planner.

Map of downtown Phoenix rail stations, with eastbound stations open April 16-mid-May and westbound stations open mid-May through July 2
Valley Metro track/street diagram

Construction will also impact vehicular traffic and pedestrian accessibility in downtown Phoenix. Restrictions include:

  • Washington St. reduced to one lane between 2nd St. and 1st Ave.
  • Washington St. direct access to northbound Central Ave. closed. Detour required.
  • Southbound 1st St. closed at Washington St. No access to Washington St.
  • Northbound 1st St. closed at Washington St. Access to Washington St. maintained.
  • Access to One North Central Bldg. west parking lot maintained on Central Ave. south of Adams St.

For more information, visit valleymetro.org/southcentral or check the Construct VM-South Central app.

The South Central Extension/Downtown Hub project team developed this work plan based on safety, ability to maintain traffic, construction scheduling and minimizing impacts to riders.